The Waterway-roadway Transport Service Company was selected as a contractor in charge of transporting the Cua Dat Hydropower Plant’s equipment. All equipment of the project were delivered at Hai Phong port and Huu Nghi border gate (Lang Son province) then transported to the site of Cua Dat Hydropower Plant by road.
Transportation time is from 2008 to 2009. The total freight volume is 3,680 tons with 32 super-sized and super-weighted packages of which two turbines weighing 65 tons/set; shipping size: (7.28 x 4.32 x 3.68) m. We has handed over the above mentioned cargo to the employer timely, ensuring the goods safety and in progress
The Cua Dat hydropower plant has the designed capacity of 104MW, located at Xuan My commune, Thuong Xuan district, Thanh Hoa province. The employer of this project is Cua Dat Hydropower JSC
Recently, the Waterway-roadway Transport Service Company has successfully transported all imported electromechanical equipment from Hai Phong port to the Nam He Hydropower Plant. . All equipment of the project were transported from Hai Phong port to the plant by road
Transportation time is from 2011 – 2012. The total freight volume is 1,320 tons with 13 super-sized and super-weighted packages, including two turbines weighing 58 tons per set
Nam He Hydroelectricity Project with a designed capacity of 36 MW, is built in Muong Tung commune, Muong Cha district, Dien Bien province, the investor is Da River JSC No. 706.
The Waterway-roadway Transport Service Company has successfully transported 1,526 tons of electromechanical equipment from Hai phong port to Dong Van Hydropower plant by road. Transportation time is from 2018 – 2019.
With the designed capacity of 34MW, Dong Van Hydropower plant is built in Dong Van commune, Que Phong district, Nghe An province. The employer of this project is the Dakrong Hydropower JSC.